DETAILED ENGINNERING DESIGN FOR THE RECONSTRUCTION OF THE ROAD SECTION: PUERTO BAQUERIZO MORENO - PROGRESO - CERRO VERDE - PUERTO CHINO (18 KM)
Client:
Ministry of Transports & Public Works
Date:
2014 - 2015
Value of Services:
600,000 USD
Funded by:
Inter-American Development Bank
Detail design of a dual-way road with the following characteristics:
- Total length: 18 Km
- Type of road: Class III
- Topography: Flat-wavy feature
- Type of Rolling: Asphalt Layer
- Section in Bridges: 15,60m
- Structures: 10
The project included upgrading works under Double Bituminous Surface Treatment, and rehabilitation and widening works of urban roads.
The project also included the following Drainage Infrastructures: (i) Road surface drainage with the drainage of stormwater runoff; (ii) Subsurface drainage with the interception and disposal of groundwater flows; (iii) Erosion protection measures for the slopes.
No items found.