FEASIBILITY STUDY, PRELIMINARY ENVIRONMENTAL IMPACT ASSESSMENT, DETAILED ENGINEERING DESIGN AND PREPARATION OF TENDER DOCUMENTS FOR REHABILITATION OF SAME - HIMO - MARANGU ROAD (93 KM) AND MOMBO - LUSHOTO (32 KM) ROAD TO BITUMEN STANDARD

Map of the Country where the project took place
Client:
Ministry of Infrastructure TANROADS (Tanzania National Roads Agency)
Date:
2011 – 2013
Value of Services:
900,000 USD
Funded by:
World Bank

Road Length: 32km

The main objective of the assignment is to undertake consultancy services on behalf of TANROADS for the

  • Feasibility study including the preliminary design, cost estimates, preliminary environmental and social assessment as well as preliminarily Resettlement Action Plan;
  • Detailed engineering design, preparation of pre-qualification and bidding documents.

The project included upgrading works under Double Bituminous Surface Treatment, and rehabilitation and widening works of urban roads.

The project also included the following Drainage Infrastructures: (i) Road surface drainage with the drainage of stormwater runoff; (ii) Subsurface drainage with the interception and disposal of groundwater flows; (iii) Erosion protection measures for the slopes.

Activities:

  • Feasibility study (Desk Study, Route Corridor selection by use of spatial analysis software like ArcGIS, Google Earth and GMap)
  • Detailed Design; (field surveys; topographical investigations, soils and materials investigations, engineering drawings, etc);
  • Environmental Impacts Assessment, Inception Report; Draft Design Report;
  • Development of Environmental and Social Management Plan and Resettlement Action Plan;

Preparation of bidding documents